First Windows

first-windows(dec13)The first two windows have been installed and they look very good however there is a problem with the window sill hanging out too far and so they need to be recessed into the window opening and to do this the builders must use a shorter bracket which has to be supplied by VelFac so further delays. Hopefully the new fitments will arrive this week and then all the windows can be installed.

With a change in the weather all the windows have to be installed before the plaster board can be fitted to give it a chance to dry out.