Piles Completed

finished-piling(aug13)The pile driving has been completed. Some of them were driven in much further than the civil engineers had thought. We had been told they might go down 7 metres before reaching stable ground however some of them went down 10 metres. Every metre costs extra!

The next stage is for a wire frame to be suspended from the piles and then encased in concrete to make a ring beam. This will take at least another two weeks so we won’t see our footprint until 23rd August.